The design cost generally includes the costs for the following:
• Outline design;
• Site investigation/testing (5% of contract value);
• Detailed design;
• Contract documentation and procurement.
By default, the design cost is calculated as a percentage of the full scheme cost.
|
Full Scheme Cost
|
Additional Cost for Design
|
|
<£50,000
|
40%
|
|
<£250,000
|
20%
|
|
<£1,000,000
|
15%
|
|
£1,000,000 +
|
12%
|