The engineering difficulty of the works can influence cost in a number of ways. The base cost applies to works on structures on a clear site or disused land in an urban environment.
A set of ‘Engineering Difficulty’ criteria, which are applicable at the activity level, is listed below along with the default uplift factor that has been assigned to each criterion.
|
Engineering Difficulty of Activities
|
Default Uplift Factor
|
|
Over Water - navigable
|
1.5
|
|
Over Water - non-navigable
|
1.0
|
|
Over Water - tidal
|
1.2
|
|
Over Water - non-tidal
|
1.0
|
|
Railway - electrified
|
3.0
|
|
Railway - non-electrified
|
2.0
|
|
Accommodating STATS - water
|
1.2
|
|
Accommodating STATS - gas
|
1.5
|
|
Accommodating STATS - electric
|
1.5
|
|
Accommodating STATS - communication cables
|
1.3
|
|
Accommodating STATS - other
|
1.1
|
|
Over Motorway or A Road
|
1.3
|
|
Over B, C or Unclassified Road
|
1.3
|
|
At height - between 2 and 5m
|
1.2
|
|
At height - between 5 and 8m
|
1.3
|
|
At height - above 8m
|
1.5
|
|
Confined space
|
3.0
|
|
Railway
|
2.0
|
|
Diversion of utility services (STATS)
|
1.5
|
|
Ground conditions
|
1.5
|
|
COSHH
|
1.5
|
|
Other Difficulty
|
1.5
|